Question: Using the schedule information below, do the following: Task Pred. Normal Crash Duration Cost Duration Cost A - - 5 d $ 8 0 3

Using the schedule information below, do the following:
Task
Pred.
Normal
Crash
Duration
Cost
Duration
Cost
A
--
5 d
$80
3 d
$200
B
--
3 d
$60
2 d
$120
C
A
4 d
$40
2 d
$240
D
B
2 d
$20
1 d
$70
E
D
4 d
$60
3 d
$160
F
C,E
3 d
$40
2 d
$120
Develop a project schedule based on normal times for each task.
What is the critical path?
The client has requested that the end date for the project be moved up by 2 days.
What is the normal cost for the overall project?How would you crash the schedule to achieve the new end date with the smallest increase in cost?What is the overall project cost for the crashed schedule derived in part B-2?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!