Question: Using the scheduling method, I need help finding the finishing and idle time. Using the priority list T3, T1, T4, T2, schedule the project below
Using the scheduling method, I need help finding the finishing and idle time.

Using the priority list T3, T1, T4, T2, schedule the project below with three processors. T1 (1) T3 (5) End T2 (4) T4 (2) Q The finishing time is: The total idle time in the schedule is
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
