Question: Activity Preceding Activity Optimistic Duration ( Days ) Most Likely Duration ( Days ) Pessimistic Duration ( Days ) Crash Cost / Day ( $
Activity Preceding Activity Optimistic Duration Days Most Likely Duration Days Pessimistic Duration Days Crash Cost Day $ Max Crash Days
a Utilizing MS Word tools, create a network diagram depicting this project.
b List the critical paths OD MLD PD
Set :
Set :
Set :
c What is the expected duration of the project?
d The project duration must be reduced by days. Which activities, in chronological order, will be crashed?
You could crash since
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
