Question: Activity Preceding Activity Optimistic Duration ( Days ) Most Likely Duration ( Days ) Pessimistic Duration ( Days ) Crash Cost / Day ( $

Activity Preceding Activity Optimistic Duration (Days) Most Likely Duration (Days) Pessimistic Duration (Days) Crash Cost / Day ($) Max Crash Days
1-162125-0
2-252836-0
311621251,2203
421013151,2252
5249138901
63,4,52837493,2306
761319242,9752
87710141,3501
971420251,2003
108,981013-0
a. Utilizing MS Word tools, create a network diagram depicting this project.
b. List the critical path(s). OD MLD PD
Set 1: 1->3->6->7->8->1088.118150
Set 2: 2->4->6->7->8->1091117151
Set 3: 2->5->6->7->9->1092123160
c. What is the expected duration of the project?
35,37,39
d. The project duration must be reduced by 5 days. Which activities, in chronological order, will be crashed?
You could crash 9,9,9,7,7 since

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!