Question: Activity Preceding Activity Optimistic Duration ( Days ) Most Likely Duration ( Days ) Pessimistic Duration ( Days ) Crash Cost / Day ( $

Activity Preceding Activity Optimistic Duration (Days) Most Likely Duration (Days) Pessimistic Duration (Days) Crash Cost / Day ($) Max Crash Days
1-162125-0
2-252836-0
311621251,2203
421013151,2252
5249138901
63,4,52837493,2306
761319242,9752
87710141,3501
971420251,2003
108,981013-0