Question: Using the table: table [ [ Activity , Duration, table [ [ Immediate ] , [ Predecessors ] ] ] , [ A

Using the table:
\table[[Activity,Duration,\table[[Immediate],[Predecessors]]],[A,4,---],[B,5,A],[C,6,A],[D,7,B,C],[E,6,C],[F,3,D,E]]
The critical path is (letters):
 Using the table: \table[[Activity,Duration,\table[[Immediate],[Predecessors]]],[A,4,---],[B,5,A],[C,6,A],[D,7,B,C],[E,6,C],[F,3,D,E]] The critical path is (letters):