Question: Using the TPL priority rule, what would be the sequence for jobs A, B, C, and D if their processing times are 4, 6, 5,

Using the TPL priority rule, what would be the sequence for jobs A, B, C, and D if their processing times are 4, 6, 5, and 2, respectively? Select one: a. DABC b. BCAD c. DCBA d. ABCD e. DACB