Question: Using thechart of activity data provided, what is the expected standard deviation for activity B? Even Nodes Time Node Activity Start Finish Optimist Pessimistic Most

Using thechart of activity data provided, what is the expected standard deviation for activity B?

Even Nodes Time Node

Activity Start Finish Optimist Pessimistic Most Likely

A1291221

B13132123

A 3.33 weeks

B 1.67 weeks

C 10 weeks

D 2.78 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!