Question: Using thechart of activity data provided, what is the expected standard deviation for activity B? Even Nodes Time Node Activity Start Finish Optimist Pessimistic Most
Using thechart of activity data provided, what is the expected standard deviation for activity B?
Even Nodes Time Node
Activity Start Finish Optimist Pessimistic Most Likely
A1291221
B13132123
A 3.33 weeks
B 1.67 weeks
C 10 weeks
D 2.78 weeks