Question: WBS Element Planned Value ( PV ) Earned Value ( EV ) Actual Cost ( AC ) 2 . 0 1 Airframe 4 8 0
WBS Element
Planned Value
PV
Earned Value
EV
Actual Cost
AC
Airframe
Engines
Avionics
Communications
Tech. Manuals
Spares
Training
Project Total
Figure Drug Surveillance Aircraft Project Monthly Performance Report
October XX
Consider the project performance report presented in figure Your analyst has determined that your estimate to complete ETC is $ Based on your performance to date and assuming future performance will proceed at the same level of efficiency as past performance, what is your estimate at completion EAC
Question Select one:
a
$
b
$
c
$
d
It can not be determined from the information provided.