Question: WBS Element Planned Value ( PV ) Earned Value ( EV ) Actual Cost ( AC ) 2 . 0 1 Airframe 4 8 0

WBS Element
Planned Value
(PV)
Earned Value
(EV)
Actual Cost
(AC)
2.01 Airframe
48000
48000
50000
2.02 Engines
22000
21000
23000
2.03 Avionics
80000
60000
45000
2.04 Communications
30000
30000
30000
2.05 Tech. Manuals
42000
40000
48000
2.06 Spares
40000
35000
42000
2.07 Training
80000
80000
86000
Project Total
342000
314000
324000
Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report
(October 31,20XX)
Consider the project performance report presented in figure 14.1. Your analyst has determined that your estimate to complete (ETC) is $224,000. Based on your performance to date and assuming future performance will proceed at the same level of efficiency as past performance, what is your estimate at completion (EAC)?
Question 14Select one:
a.
$548,000
b.
$550,000
c.
$568,000
d.
It can not be determined from the information provided.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!