Question: WBS Element Planned Value ( PV ) Earned Value ( EV ) Actual Cost ( AC ) 2 . 0 1 Airframe 4 8 0

WBS Element
Planned Value
(PV)
Earned Value
(EV)
Actual Cost
(AC)
2.01 Airframe
48000
48000
50000
2.02 Engines
22000
21000
23000
2.03 Avionics
80000
60000
45000
2.04 Communications
30000
30000
30000
2.05 Tech. Manuals
42000
42000
48000
2.06 Spares
40000
35000
42000
2.07 Training
80000
80000
86000
Project Total
342000
316000
324000
Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report
(October 31,20XX)
Consider the project performance report presented in figure 14.1. What valid conclusion can you draw regarding the project schedule performance as of October 31,20XX?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!