Question: WBS Element Planned Value ( PV ) Earned Value ( EV ) Actual Cost ( AC ) 2 . 0 1 Airframe 4 8 ,

WBS Element
Planned Value
(PV)
Earned Value
(EV)
Actual Cost
(AC)
2.01 Airframe
48,000
48,000
50,000
2.02 Engines
22,000
21,000
23,000
2.03 Avionics
80,000
60,000
45,000
2.04 Communications
30,000
30,000
30,000
2.05 Tech. Manuals
42,000
42,000
48,000
2.06 Spares
40,000
35,000
42,000
2.07 Training
80,000
80,000
86,000
Project Total
342,000
316,000
324,000
Drug Surveillance Aircraft ProjectMonthly Performance Report
(October 31,20XX)
Consider the project performance report presented in the Figure above. As a project manager these results should lead you to:
WBS Element
Planned Value
(PV)
Earned Value
(EV)
Actual Cost
(AC)
2.01 Airframe
48,000
48,000
50,000
2.02 Engines
22,000
21,000
23,000
2.03 Avionics
80,000
60,000
45,000
2.04 Communications
30,000
30,000
30,000
2.05 Tech. Manuals
42,000
42,000
48,000
2.06 Spares
40,000
35,000
42,000
2.07 Training
80,000
80,000
86,000
Project Total
342,000
316,000
324,000
Drug Surveillance Aircraft ProjectMonthly Performance Report
(October 31,20XX)
Consider the project performance report presented in the Figure above. As a project manager these results should lead you to:
take actions to understand and remedy the schedule performance on the active training work packages.
take actions to understand and resolve budgetary overruns on the active communications work packages.
take actions to understand and remedy the schedule performance on the active avionics work packages.
notify the project owner that you will not require all of the funding currently budgeted for this project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!