Question: WBS Element Planned Value (PV) Earned Value (EV) Actual Cost (AC) 2.01 Airframe 48000 48000 50000 2.02 Engines 22000 21000 23000 2.03 Avionics 80000 60000
WBS Element | Planned Value (PV) | Earned Value (EV) | Actual Cost (AC) |
| 2.01 Airframe | 48000 | 48000 | 50000 |
| 2.02 Engines | 22000 | 21000 | 23000 |
| 2.03 Avionics | 80000 | 60000 | 45000 |
| 2.04 Communications | 30000 | 30000 | 30000 |
| 2.05 Tech. Manuals | 42000 | 42000 | 48000 |
| 2.06 Spares | 40000 | 35000 | 42000 |
| 2.07 Training | 80000 | 80000 | 86000 |
| Project Total | 342000 | 316000 | 324000 |
(October 31, 20XX)
Consider the project performance report presented in figure 14.1. What valid conclusion can you draw regarding the project cost performance as of October 31, 20XX?
Step by Step Solution
3.48 Rating (158 Votes )
There are 3 Steps involved in it
Answer To identify the undervalued or overvalued performance we need to compare ... View full answer
Get step-by-step solutions from verified subject matter experts
