Question: We are now part way through a project at a point where we had planned to have 6 7 % of the work done. We

We are now part way through a project at a point where we had planned to have 67% of the work done. We have spent $324,008 of the total budget of $886,285. We have completed 51% of the activities. WHAT IS THE etc