Question: What data does the Integrated Program Management Report (IPMR) Format 3 detail? (IMAGE DESCRIPTION: IPMR Format 3 sample shows section 6, Performance Data, which includes

What data does the Integrated Program Management Report (IPMR) Format 3 detail?

(IMAGE DESCRIPTION: IPMR Format 3 sample shows section 6, Performance Data, which includes representative values for the PMB at the beginning and end of the period, authorized baseline changes, management reserve, and the total budget. Representative values for the PMB at the beginning and end of the period, and authorized baseline changes include: BCWS cumulative to date; BCWS for the reporting period; BCWS for a six period forecast; BCWS by quarter; the to complete value; undistributed budget; and total budget.)

IMPR Format 3 is limited to detailing only the current reporting period budgeted cost for work scheduled (BCWS)data

IMPR Format 3 details current budgeted cost for work scheduled (BCWS), cumulative BCWS data for the beginning and end of the current period, but it does not include any forecasted BCWS.

IMPR Format 3 details current budgeted cost for work scheduled (BCWS), cumulative BCWS data for the beginning and end of the current period, and forecasted BCWS for future reporting periods.

IMPR Format 3 details current and cumulative budgeted cost for work scheduled (BCWS)data for the current period, as well as cumulative budgeted cost for work performed (BCWP)for future reporting periods.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!