Question: What useful information does this Integrated Program Management Report (IPMR) extract provide an analyst about estimates at completion (EACs)? (IMAGE DESCRIPTION: An excerpt from Integrated
| What useful information does this Integrated Program Management Report (IPMR) extract provide an analyst about estimates at completion (EACs)? (IMAGE DESCRIPTION: An excerpt from Integrated Program Management Report (IPMR) Format 1 displays performance data for the following WBS elements: 1.1 Prime Vehicle; 1.1.1 Frame; 1.1.2 Suspension/Steering; 1.1.3 Power Package; and 1.1.3.1 Engine. Format. Data includes: current and cumulative to date BCWS, BCWP, ACWP, and cost and schedule variances. Format 1 also displays budgeted and estimated at completion values for each element, and the variance between the two values.) |
| This portion of the IPMR shows the contractor managements best case, worst case, and most likely case EACs. |
| This portion of the IPMR shows the contractors original EAC by Work Breakdown Structure (WBS) element, but these estimates are not required to be updated to reflect the latest available information. |
| This portion of the IPMR shows the worst case management EACs for the authorized contractual scope. |
This portion of the IPMR shows the contractors EAC, updated to reflect the latest information, by Work Breakdown Structure (WBS) element. |