Question: What happens to the project duration ( working days ) when the project is resource constrained and overallocations are resolved by leveling outside of slack?
What happens to the project duration working days when the project is resource constrained and overallocations are resolved by leveling outside of slack?
Question options:
The project duration is increase by days.
The project duration is increased by days.
The project duration is unchanged.
None of the above