Question: What important Scrum artifact is used to graphically display progress on each sprint during the monitoring and controlling process? Group of answer choices WBS burndown

What important Scrum artifact is used to graphically display progress on each sprint during the monitoring and controlling process?
Group of answer choices
WBS
burndown chart
sprint backlog
product backlog