Question: What is being calculated in a Critical Path Analysis Backward Pass? a. the Late Start and Late Finish for each activity and float of non-critical
What is being calculated in a Critical Path Analysis Backward Pass?
a.
the Late Start and Late Finish for each activity and float of non-critical paths
b.
the Early Start and Early Finish for each activity and float of non-critical paths
c.
the duration and float of the other paths
d.
the duration of the critical path itself