Question: What is the cost variance (CV), if earned value (EV) is $500, actual cost (AC) is $700, and the planned value (PV) is $650. Group

What is the cost variance (CV), if earned value (EV) is $500, actual cost (AC) is $700, and the planned value (PV) is $650.

Group of answer choices

-100

100

200

-200