Question: What is the cost variance (CV), if earned value (EV) is $900, actual cost (AC) is $700, and the planned value (PV) is $650. Group
What is the cost variance (CV), if earned value (EV) is $900, actual cost (AC) is $700, and the planned value (PV) is $650.
Group of answer choices
100
-200
-100
200