Question: What is the critical path doing the forward and backward pass and building a network Immediate predecessors Activity Time Estimate b-a. a m b 8

What is the critical path doing the forward and

What is the critical path doing the forward and backward pass and building a network

Immediate predecessors Activity Time Estimate b-a. a m b 8 16 15 30 63 A B C D E F Expected Times (ET) Activity Variances a + 4m+b ET = 0 = 6 6 6 15 5.44 29 13.44 60 18.78 45 21.78 36 11.11 10 0.44 16 2.78 15 7.11 B A C,D 41 25 22 38 67 53 50 12 23 19 48 34 A 30 8 13 10 15 G . B E,F,G 3 17 What is the Crticial Pat 0 0 A(15) 0 0 0 0 0 0 o D B(29) A(O) 0 0 0 0 0