Question: What is the critical path for the same table? Activity Normal Immediate Predecessors Normal Time ( weeks ) A None 4 B A 9 C

What is the critical path for the same table?
Activity Normal Immediate Predecessors Normal Time (weeks)
A None 4
B A 9
C A 4
D B, C 6
E C 8
F D 3
G E, F 4