Question: What is the current critical path? Which activity to crash first? After crashing 1 week, what is the new critical path(s)? Which activity or activities

What is the current critical path? Which activity

  1. What is the current critical path?
  2. Which activity to crash first?
  3. After crashing 1 week, what is the new critical path(s)?
  4. Which activity or activities to crash then?
  5. What is the total cost?
Activity Crash Cost/week ($) Max Crash Possible (weeks) A 2 $115,000 $95,000 2 D o E 2 $50,000 $40,000 1 2334 24 35 Legend: F G H ESEF LS LF 0 $80,000 $100,000 7 1 9 123 9 123 3542 35 42 019 09 A 19) C(14) 6(71 D(10) (E (12) 9 19 1121 118) 2335 2335 42/50 4250 H(21) 1940 2142