Question: what is the minimum possible project duration?How much extra will it cost? The client has requested to reduce the project duration by 5 days for

what is the minimum possible project duration?How much extra will it cost?

The client has requested to reduce the project duration by 5 days for which they will pay Rs 500 extra. Do you the this is an attractive deal for you?

The client informs that they have extra Rs 1500 which they can provide for crashing. What would you tell them about the number of days that would be crashed with this amount?

what is the minimum possible project duration?How

\begin{tabular}{|l|l|l|l|l|l|} \hline & & \multicolumn{2}{|c|}{ Time (days) } & \multicolumn{2}{l|}{ Cost (NPR) } \\ \hline Activity & Predecessors & Vormal & Crash & Normal & Crash \\ \hline A & & 6 & Not possible & 400 & 400 \\ \hline B & & 8 & 6 & 300 & 400 \\ \hline C & A & 8 & 7 & 500 & 575 \\ \hline D & B, C & 6 & 3 & 300 & 600 \\ \hline E & B, C & 10 & 8 & 300 & 420 \\ \hline F & A & 14 & 12 & 400 & 640 \\ \hline G & D & 12 & 9 & 600 & 870 \\ \hline H & E, F & 6 & Not possible & 500 & 500 \\ \hline I & G, H & 8 & Not possible & 700 & 700 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!