Question: What is the probability that project will be completed between 31 and 35 weeks. Critical path is B-D-E-F. a. 49% b. 64% c. 85% d.

What is the probability that project will be

What is the probability that project will be completed between 31 and 35 weeks. Critical path is B-D-E-F.

a. 49%

b. 64%

c. 85%

d. 51%

Immediate Optimistic Most Likely Pessimistic Expected Activity Predecessors a b Time t Variance 0 o m A 4 6 14 7 2.7778 -- B 4 9 14 9 2.7778 C A 6 13 14 12 1.7778 D 4 8 12 8 1.7778 A, B E D 2 10 12 2.7778 D 9 F 5 5 11 C, E 6 1 2 2 E 5 8 5 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!