Question: What is the project completion date? ACT PRED NORMAL TIME (WEEKS) A 3 B 2 C A,B 4 D C 3 E B 2 F

What is the project completion date?

ACT PRED NORMAL TIME (WEEKS)
A 3
B 2
C A,B 4
D C 3
E B 2
F D,E 2