Question: What is the takt time? The manager at Ormonde Inc. collected the value stream mapping data from the plant's most problematic manufacturing cell that fabricates
What is the takt time?

The manager at Ormonde Inc. collected the value stream mapping data from the plant's most problematic manufacturing cell that fabricates parts for washing machines. This data is shown in Table 1. Using this data, calculate the current state performance of the cell and answer the following questions. LOADING... Click the icon to view Table 1. a. What is the cell's current inventory level? The cell's current inventory level is 2250 parts. (Enter your response as a whole number.) b. What is the takt time for this manufacturing cell? The takt time is nothing minutes. (Enter your response rounded to two decimal places.)
Overall Process Attributes Process Step 1 Process Step 2 Average demand: 500/day Batch size: 20 Number of shifts per day: 3 Availability: 8 hours per shift with a 45 minute lunch break Cutting Cycle time = 115 seconds Setup time = 3 minutes Up time = 100% Operators = 1 WIP = 300 units (before Cutting) Bending Cycle time = 250 seconds Setup time = 5 minutes Up time = 90% Operators = 2 WIP = 550 units (before Bending) Punching Cycle time = 140 seconds Setup time = none Up time = 100% Operators = 1 WIP = 200 units (Before Punching) WIP = 1,200 units (After Punching) One shipment of 2,500 units each week Process Step 3 Supplier Information Information Flow All communications with customer are electronic There is a weekly order release to Cutting All material is pushedStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts