Question: The manager at Ormonde Inc. collected the value stream mapping data from the plant's most problematic manufacturing cell that fabricates parts for washing machines. This

The manager at Ormonde Inc. collected the value stream mapping data from the plant's most problematic manufacturing cell that fabricates parts for washing machines. This data is shown in Table 1. Using this data, calculate the current state performance of the cell and answer the following questions

a. What is the cell's current inventory level?

The cell's current inventory level is _________(Enter your response as a whole number.)

b. What is the takt time for this manufacturing cell?

The takt time is _____ minutes (The cell's takt time is the rate at which the cell must produce units in order to match demand. It can be caluclated as ratio of the time availability in a day (daily availability) and the daily demand of parts). Enter your response rounded to two decimal places

c. What is the production lead time at each process in the manufacturing cell? Complete the table

Interval Lead Time

Before Cutting ______

Between Cutting and Bending ______

Between Bending and Punching _____

After Punching _______

d. There's a total processing time of this manufacturing cell? ________ secondsThe manager at Ormonde Inc. collected the value

e. What is the capacity of this manufacturing cell? ________ units

The cell's current inve - X More info Overall Process Attributes Process Step 1 Process Step 2 Average demand: 520/day Batch size: 30 Number of shifts per day: 3 Availability: 8 hours per shift with a 45 minute lunch break Cutting Cycle time = 126 seconds Setup time = 4 minutes Up time = 100% Operators = 1 WIP = 350 units (before Cutting) Bending Cycle time = 240 seconds Setup time = 7 minutes Up time = 90% Operators = 2 WIP = 600 units (before Bending) Punching Cycle time = 130 seconds Setup time = none Up time = 100% Operators = 1 WIP = 200 units (Before Punching) WIP = 1,000 units (After Punching) One shipment of 2,600 units each week Process Step 3 Supplier Information Information Flow All communications with customer are electronic There is a weekly order release to Cutting All material is pushed Print Done

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!