Question: What is the total float in activity F? Activities Predecessor Duration A None 4 B A 2 C A 4 D C 5 E B,
What is the total float in activity F? Activities Predecessor Duration A None 4 B A 2 C A 4 D C 5 E B, C 6 F D 2 G D 5 H G 4 Group of answer choices 0 days 2 days 7 days 10 days