Question: When is the proper time to plan for events that are not happening according to the project plan? a. as the unanticipated events occur because

When is the proper time to plan for events that are not happening according to the project plan?

a. as the unanticipated events occur because this process saves you valuable time 

b. contingency planning should occur throughout the project life cycle 

c. this is not a function of project management and it is not required 

d. contingency planning should only occur in the design phasen

Step by Step Solution

3.54 Rating (158 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The correct option is B contingency planning should occur th... View full answer