Question: When it comes to closing the change management process, what is the key condition? Select one: O a. Change outcomes have been approved for transfer
When it comes to closing the change management process, what is the key condition?
Select one:
O a.
Change outcomes have been approved for transfer to relevant operational owners
O b.
A comprehensive stakeholder satisfaction survey has been conducted and assessed
O c.
The funds allocated to the project are spent and no further allocation is anticipated
O d. A change management program evaluation has been conducted by the sponsor