Question: When it comes to closing the change management process, what is the key condition? Select one: O a. Change outcomes have been approved for transfer

When it comes to closing the change management process, what is the key condition?
Select one:
O a.
Change outcomes have been approved for transfer to relevant operational owners
O b.
A comprehensive stakeholder satisfaction survey has been conducted and assessed
O c.
The funds allocated to the project are spent and no further allocation is anticipated
O d. A change management program evaluation has been conducted by the sponsor

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!