Question: When tasks, such as the highlighted tasks below, are indented in MS-Project or similar software this means: The tasks are predecessors of the prior task

 When tasks, such as the highlighted tasks below, are indented in

When tasks, such as the highlighted tasks below, are indented in MS-Project or similar software this means: The tasks are predecessors of the prior task in the outline The tasks are off the critical path The tasks are less important The tasks are subtasks of a summary-level task