Question: When tasks, such as the highlighted tasks below, are indented in MS-Project or similar software this means: The tasks are predecessors of the prior task

When tasks, such as the highlighted tasks below, are indented in MS-Project or similar software this means: The tasks are predecessors of the prior task in the outline The tasks are off the critical path The tasks are less important The tasks are subtasks of a summary-level task