Question: When there are multiple critical paths and the project duration must be reduced, it is necessary to make reductions: . ) on whichever non -
When there are multiple critical paths and the project duration must be reduced, it is necessary to make reductions: on whichever noncritical path affords the smallest cost increase
that will shorten all of the critical paths
that will shorten all of the noncritical paths
on whichever critical path affords the smallest cost increase which option is correct