Question: When tracking a project's progress, in order to know if a project is behind schedule one must compare actual cost to budgeted cost of work

When tracking a project's progress, in order to

When tracking a project's progress, in order to know if a project is behind schedule one must compare actual cost to budgeted cost of work scheduled budgeted cost of work performed to budgeted cost of work scheduled actual cost to budgeted cost of work performed actual cost to budgeted cost Question 16 5 pts To identify slack at a task in a project compare the early start to late start early start to early finish late start to early finish late finish to late start