Question: When would you apply learning curve method for estimating project times and costs? Question 2 5 Answer a . When work packages have high uncertainty

When would you apply learning curve method for estimating project times and costs?
Question 25Answer
a.
When work packages have high uncertainty
b.
When detailed accuracy is crucial
c.
When the same task or product is repeated several times
d.
When historical data is scarce