Question: Which of the following is a wrong statement a PERT is suitable for projects having probabilistic time estimates b CPM is suitable for projects having

Which of the following is a wrong statement
a PERT is suitable for projects having probabilistic time estimates
b CPM is suitable for projects having deterministic activities
c Both CPM and PERT are event oriented
d PERT is event oriented, while CPM is activity oriented