Question: Which one is the bottleneck? What is the process capacity? What is the flow rate if demand is 8 units per hour? What is the
Which one is the bottleneck?
What is the process capacity?
What is the flow rate if demand is 8 units per hour?
What is the utilization of each resource if the demand is 8 units per hour?
Consider a process consisting of three resources: 1 2 3 Resource Processing Time (min/unit) Number of Workers 1 10 2 2 6 1 3 16 3Step by Step Solution