Question: Which one is the bottleneck? What is the process capacity? What is the flow rate if demand is 8 units per hour? What is the

Which one is the bottleneck? What is the processWhich one is the bottleneck?

What is the process capacity?

What is the flow rate if demand is 8 units per hour?

What is the utilization of each resource if the demand is 8 units per hour?

Consider a process consisting of three resources: 1 2 3 Resource Processing Time (min/unit) Number of Workers 1 10 2 2 6 1 3 16 3