Question: Which statement about the project critical path is true? A. The critical path always has zero total float, and it shows the earliest possible time
Which statement about the project critical path is true? A. The critical path always has zero total float, and it shows the earliest possible time to complete the project B. The critical path can have zero, positive, or negative float. C. A project can have only one critical path D. The critical path consumes the biggest portion of the project budget compared to other paths
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
