Question: Which statement applies? a. There are 12 activities so total free slack is 12. b. There is no total slack on any activity but there

Which statement applies? a. There are 12Which statement applies?

a. There are 12 activities so total free slack is 12.

b. There is no total slack on any activity but there is free slack on the merge activities.

c. There is no total slack on any activity but there is free slack on the burst activities.

d. There is no total slack and no free slack on any activity.

How sensitive is the network schedule?

a. Not very sensitive. There are three paths that make up the critical path.

b. Very sensitive. There are three paths that make up the critical path.

c. Not very sensitive. There is no slack on any activity.

EX6-9 (Algo) You are creating a customer database... You are creating a customer database for the Hillsboro Hops minor league baseball team. Given the information below, complete the forward and backward pass, compute activity slack, and identify the critical path. ID Predecessor A B None A Time (days) 7 4 4 B Description Systems Subsystem A design Subsystem B design Subsystem C design Program A Program B Program c Subsystem A Subsystem B Subsystem C Integration Integration test 2 2 H D E F G H, I, J K J K L 3 The project will take The early start on Activity Dis The late start on Activity E is The late finish on Activity is days. days. days. days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!