Question: Which statement is true regarding integrated change control? Question 4 Select one: a. it should be performed during project closing b. it is best performed

Which statement is true regarding integrated change control? Question 4 Select one: a. it should be performed during project closing b. it is best performed during project planning c. it is usually conducted through project team voting d. it is the process of identifying, evaluating, and managing changes throughout the project's life cycle