Question: which the machine is not working. The machine also has 3.5 hours a week without any work scheduled. When the machine is running, it averages
which the machine is not working. The machine also has 3.5 hours a week without any work scheduled. When the machine is running, it averages 96% rated speed. After production, 2.5% of the parts processed are found to be defective. For the problem above, what is the value of the OEE (rounded to the nearest two decimal places)?
67.78%
74.55%
52.81%
53.01%
None of the above
Step by Step Solution
There are 3 Steps involved in it