Question: Why and how is the answer A ? 4 1 ) Given the cost information in the table, what is the cheapest activity to crash

Why and how is the answer A?41) Given the cost information in the table, what is the cheapest activity to crash on a per week basis? Normal Normal Crash Crash Activity Time Cost Time Cost JA 8 $1,0005 $6,000 B 62,00046,000 C 92,50068,000 D 124,000810,000 A) Activity A B) Activity B C) Activity C D) Activity D Answer: A Diff: 2 ai 10201.:. D ai