Question: With the project data included in the table, answer the questions. Include a file with the complete process that evidences your analysis. Answer the following

With the project data included in the table, answer the questions. Include a file with the complete process that evidences your analysis.

Answer the following questions:

1. Using the data in the included table, build the node network for the project. (5 points)

a. How long will the project take to complete?

b. What is or are the critical path(s)?

c. What activities do you have time to spare and how much?

2. What is the minimum cost to accelerate the project in 2 weeks? (15 points) (You must do the node network to determine the critical path as many times as necessary to determine the minimum cost of accelerating the project in 2 weeks)

With the project data included in the table,

Activity Cost normal Precedents Time normal (weeks) Cost of acceleration Time of acceleration (weeks) 6 B C D E F 7 2 4 5 2 4 5 1 3 4 1 2 4 7000 5000 9000 3000 2000 4000 5000 8000 7000 10200 4500 3000 7000 8000 A . B, C D D E, F G

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!