Question: Without using PERT, the duration estimate for activity A would be 5 workdays. Suppose an optimistic time estimate for this activity is 2 workdays, and
Without using PERT, the duration estimate for activity A would be workdays. Suppose an optimistic time estimate for this activity is workdays, and a pessimistic time estimate is workdays.