Question: Work Breakdown Structure 1.1 Uniforms 1.1.1 Select uniform design 1.1.2 Player measurements 1.1.3 Compile and place order 1.2 Practice 1.2.1 Finalize and distribute practice schedule

Work Breakdown Structure 1.1 Uniforms 1.1.1
Work Breakdown Structure 1.1 Uniforms 1.1.1 Select uniform design 1.1.2 Player measurements 1.1.3 Compile and place order 1.2 Practice 1.2.1 Finalize and distribute practice schedule 1.2.2 Summer practices 1.2.3 Hold final scrimmages 40. Given the preceding Work Breakdown Structure for a team to prepare for a Fall soccer tournament, which of the following items is not in alignment with the 8/80 rule? A Player measurements Practice C. Summer practices D. Hold final scrimmages