Question: Work Breakdown Structure (WBS) for a project to improve the delivery services of ABATA Courier Services. The WBS is broken down into four levels of
Work Breakdown Structure (WBS) for a project to improve the delivery services of ABATA Courier Services. The WBS is broken down into four levels of decomposition and aligns with the SDLC Phases of Planning, Design, Implementation, and Testing. The budget and resources allocation for each task are also included.
Level 1: Project Management
Budget: RM50,000
Project Manager: 200 hours
Project Coordinator: 150 hours
Project Sponsor: 50 hours
Level 2: Planning Phase
Budget: RM100,000
Stakeholder Analysis: 50 hours
Requirements Gathering: 100 hours
Feasibility Study: 75 hours
Risk Assessment: 25 hours
Level 3: Design Phase
Budget: RM100,000
System Architecture: 50 hours
User Interface Design: 75 hours
Database Design: 100 hours
Technical Specifications: 75 hours
Level 4: Implementation Phase
Budget: RM150,000
Automation Development: 300 hours
Package tracking system: 150 hours
Automated sorting system: 100 hours
Billing and payment system: 50 hours
Data Analytics Development: 400 hours
Data collection and analysis: 150 hours
Performance analysis: 150 hours
Predictive analysis: 100 hours
Logistics Optimization: 100 hours
Green IT Implementation: 50 hours
Level 4: Testing Phase
Budget: RM50,000
Unit Testing: 50 hours
Integration Testing: 75 hours
System Testing: 100 hours
User Acceptance Testing: 75 hours
1) Create a network diagram with the above work breakdown structure and calculate the critical path