Question: WP 1 2 10 11 A 2 0 2 B ONO 15 oooo 4 6 Schedule information Baseline budget needs DUR ES LF Total Time

WP 1 2 10 11 A 2 0 2 B ONO 15 oooo 4 6 Schedule

WP 1 2 10 11 A 2 0 2 B ONO 15 oooo 4 6 Schedule information Baseline budget needs DUR ES LF Total Time period SL PV 6 3 4 5 6 7 8 9 20 10 10 2 2 6 2 5 10 2 100 20 30 30 20 3 2 6 35 15 10 10 120 30 40 50 2 9 11 0 30 10 20 Total PV by period 10 10 40 50 40 20 30 40 50 10 20 Cumulative PV by period 10 20 60 110 150 170 200 240 290 300 320 0 D 1 E 3 6 9 0 F 0 Period 3: Task % Complete EV AC PV CV SV A Finished 30 B 33% 10 C 20% 30 D 60% 20 Cumulative Totals 90 Quesitons: What is the CV, SV, CPI, SPI and PCIB at the Period 3? What do they mean in terms of performance