Question: You and your team are determining the activity duration estimates for the project. You requested that each team member determine the estimates by multiplying the

You and your team are determining the activity duration estimates for the project. You requested that each team member determine the estimates by multiplying the quantity of work with the historical productivity rate of the individual department. This is an example of what technique to generate estimates?

Group of answer choices

a. Bottom-up estimating

b. Parametric estimating

c. Three point estimating

d. Analogous estimating