Question: You are developing a performance progress report for a project you are managing. The following time-phased budget was developed earlier in the planning stage and
You are developing a performance progress report for a project you are managing. The following time-phased budget was developed earlier in the planning stage and is being used as the standard against which the project performance is measured. Work Packages W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 A 10 2 9 B 10 1 7 C 8 6 2 10 8 Total 10 2 9 10 1 7 8 6 2 10 8 You are analyzing the project performance at the end of Week 5. Activity "B" is 40% complete and its actual cost is 15. What is the Schedule Performance Index of this activity? Use two decimal places in your calculations.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
