Question: You are evaluating a 4-year project, and its cash flows are -61000, 23000, 18000, 25000, 21000 for years 0 to 4, respectively. What is

You are evaluating a 4-year project, and its cash flows are -61000,

You are evaluating a 4-year project, and its cash flows are -61000, 23000, 18000, 25000, 21000 for years 0 to 4, respectively. What is the project's IRR? 12.8% 13.9% 14.9% 15.9% 17.1% 18.2%