Question: You are managing a program to develop and deploy a high-resolution imagery satellite. The system requires that a specific technical specification be met, which will
You are managing a program to develop and deploy a high-resolution imagery satellite. The system requires that a specific technical specification be met, which will require heavy research and testing. Which of the following risk monitoring tools would be most appropriate for progress management and reporting?
() Technical Performance Measurements (TPMs)
() Risk Identification Template
() Risk Reporting Matrix
() Earned Value Analysis